Question Related to COCOMO model – 1

Suppose that a project was estimated to be 400 KLOC. Calculate effort & time for each of 3 modes of development.

Software Product Type a b c d
Organic 2.4 1.05 2.5 0.38
Semi-detached 3.0 1.12 2.5 0.35
Embedded 3.6 1.20 2.5 0.32

Solution:

As we know that 3 modes of development are

  1. Organic
  2. Semi-detached
  3. Embedded

Also we know that

Effort = a (KLOC)b person month

Time = c (Effort)d Months

Here, we are given KLOC = 400

Organic:

Effort = a (KLOC)b person month

= 2.4 (400)1.05 person month

= 1295 person month

Time = c (Effort) d Months

= 2.5 (1295) 0.38 Months

= 38 Months

Semi-detached:

Effort = a (KLOC)b person month

= 3 (400)1.12 person month

= 2462 person month

Time = c (Effort) d Months

= 2.5 (2462) 0.35 Months

= 38.4 Months

Embedded

Effort = a (KLOC)b person month

= 3.6 (400)1.2 person month

= 4772 person month

Time = c (Effort) d Months

= 2.5 (4772) 0.32 Months

= 38 Months